Tunnelling breakthrough at Farnworth Tunnel

Listen to this article

Tunnel boring machine (TBM) Fillie has broken through at Farnworth Tunnel, completing a tunnelling drive at the centre of the North West electrification project.

Network Rail and contractor J. Murphy & Sons are enlarging one of the 19th century bores to accommodate a double-track railway and overhead line equipment.

Electrification of the route between Manchester and Bolton has involved filling the up-tunnel with foam concrete and re-boring it. Meanwhile, the down-tunnel was strengthened to allow single-line working while the tunnelling was taking place.

It hasn’t been entirely straightforward for the project teams. Loose sands , which hadn’t been picked up by initial ground investigations, ran into the excavated area early in the boring programme, setting back the original completion date.

Murphy’s project manager Mick Boyle said: “Breaking through with the TBM yesterday is a big step to ensuring that the tunnel is secured for many decades of providing a more efficient railway for Network Rail and passengers.

“This has been an exciting project to work on and demonstrates the skills of our team who have worked very hard to ensure that we have reached this milestone.”

Photo courtesy of Murphy/ Mullholland Media.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Latest Rail News

Labour pledges to renationalise rail: reaction

The Labour party has set out its plan for rail, ahead of this year’s general election, with pledges to...

More like this...